  "html_url": "https://licitia.com.mx/licitacion/lo-16-b00-016b00002-n-17-2023",
  "canonical": "https://licitia.com.mx/licitacion/lo-16-b00-016b00002-n-17-2023",
  "id": "09e9802c317d434ca23fbd4676700773",
  "procedure_number": "LO-16-B00-016B00002-N-17-2023",
  "file_number": "E-2023-00020181",
  "title": "CONTINUACION DEL CPMI PICACHOS KM 52 AL 56, PROYECTO BALUARTE-PRESIDIO, SINALOA.",
  "description": {
    "short": null,
    "detailed": "CONTINUACIÓN DE LA CONSTRUCCIÓN DEL CANAL PRINCIPAL MARGEN IZQUIERDA DE LA ZONA DE RIEGO DE LA PRESA DE ALMACENAMIENTO PICACHOS DEL KM 52+000 AL KM 56+000, INCLUYE: ESTRUCTURAS, PROYECTO BALUARTE-PRESIDIO, MUNICIPIO DE MAZATLÁN, ESTADO DE SINALOA"
  },
  "lifecycle": {
    "section": "concluido",
    "source_status": "ADJUDICADO",
    "moved_at": null
  },
  "buyer": {
    "agency": "CONAGUA",
    "acronym": "CONAGUA",
    "branch": "16 - MEDIO AMBIENTE Y RECURSOS NATURALES",
    "buying_unit": "DIRECCION GENERAL DEL ORGANISMO DE CUENCA PACIFICO NORTE",
    "requesting_unit": "unidad requiriente data",
    "requesting_group": "DIRECCION GENERAL DEL ORGANISMO DE CUENCA PACIFICO NORTE",
    "entity": null,
    "slug": "conagua",
    "unit_slug": "direccion-general-del-organismo-de-cuenca-pacifico-norte-016b00002"
  },
  "classification": {
    "procedure_type": "LICITACIÓN PÚBLICA",
    "contracting_type": "OBRA PÚBLICA",
    "publication_type": null,
    "character": "NACIONAL",
    "fiscal_year": 2023,
    "law": "LEY DE OBRAS PÚBLICAS Y SERVICIOS RELACIONADOS CON LAS MISMAS",
    "legal_basis_id": null,
    "exception_basis": null,
    "internal_control_number": "PC-016B00002-E12-2023",
    "supply_source_number": null
  },
  "schedule": {
    "published_at": "2023-04-18T00:38:04.000Z",
    "clarification_meeting_at": "2023-04-21T17:00:00.000Z",
    "clarification_questions_deadline_at": "2023-04-20T17:00:00.000Z",
    "clarification_responses_deadline_at": null,
    "bid_opening_at": "2023-04-28T18:30:00.000Z",
    "award_at": "2023-05-30T00:00:00.000Z",
    "estimated_contract_at": "2023-06-01T06:00:00.000Z",
    "site_visit_at": "2023-04-20T18:00:00.000Z",
    "estimated_work_start_at": "2023-06-01T06:00:00.000Z"
  },
  "estimated_value": {
    "minimum": null,
    "maximum": null,
    "currency": "MXN",
    "updated_at": null
  },
  "lots": [
    {
      "number": "1",
      "name": "PARTIDA SOLA",
      "description": "PARTIDA SOLA",
      "requirement_group_id": "1",
      "items": [
        {
          "number": "1",
          "cucop_code": "62601-0009",
          "specific_item_code": "62601",
          "cucop_description": "CONSTRUCCION DE CANAL",
          "description": "CONTINUACIÓN  DE LA CONSTRUCCIÓN DEL CANAL PRINCIPAL MARGEN IZQUIERDA DE LA ZONA DE RIEGO DE LA PRESA  DE ALMACENAMIENTO PICACHOS DEL KM 52+000 AL KM 56+000, INCLUYE: ESTRUCTURAS, PROYECTO BALUARTE - PRESIDIO, MUNICIPIO DE ROSARIO, ESTADO DE SINALOA",
          "requested_quantity": null,
          "minimum_quantity": null,
          "maximum_quantity": "1",
          "unit": null,
          "minimum_amount": null,
          "maximum_amount": null
        }
      ]
    }
  ],
  "awards": [
    {
      "id": "C-2023-00047186",
      "internal_reference": "2023-B05-B28-CA-25-RF-LP-A-OR-0028",
      "title": "CONTINUACION DEL CPMI PICACHOS KM 52 AL 56, PROYECTO BALUARTE-PRESIDIO, SINALOA.",
      "status": "PUBLICADO",
      "contractor": {
        "name": "URBANIZACIONES AGV SA DE CV",
        "normalized_name": "URBANIZACIONES AGV",
        "rfc_type": null,
        "slug": "urbanizaciones-agv"
      },
      "contract_period": {
        "published_at": "2023-05-30T13:26:50.000Z",
        "starts_at": "2023-06-01T06:00:00.000Z",
        "ends_at": "2023-11-27T06:00:00.000Z"
      },
      "value": {
        "subtotal": "74832631.66",
        "tax": "11973221.06",
        "total": "86805852.72",
        "maximum_subtotal": "0",
        "maximum_total": "0",
        "currency": "MXN"
      },
      "open_contract_type": null,
      "quantity": null,
      "exercised_quantity": null,
      "participants": [],
      "line_items": [
        {
          "number": "0",
          "cucop_code": "62601-0009",
          "description": "CONTINUACIÓN  DE LA CONSTRUCCIÓN DEL CANAL PRINCIPAL MARGEN IZQUIERDA DE LA ZONA DE RIEGO DE LA PRESA  DE ALMACENAMIENTO PICACHOS DEL KM 52+000 AL KM 56+000, INCLUYE: ESTRUCTURAS, PROYECTO BALUARTE - PRESIDIO, MUNICIPIO DE ROSARIO, ESTADO DE SINALOA",
          "unit": null,
          "requested_quantity": null,
          "awarded_quantity": null,
          "unit_price": null,
          "subtotal": "74832631.66",
          "tax": "11973221.06",
          "other_taxes": null,
          "total": "86805852.72"
        }
      ]
    }
  ],
  "documents": [
    {
      "id": null,
      "annex_number": 1,
      "document_type": null,
      "description": "CONVOCATORIA",
      "filename": "01.01 Proyecto de Convocatoria LO-16-B00-016B00002-N-17-2023.docx",
      "availability": "available",
      "size_bytes": "497170",
      "mime_type": "application/vnd.openxmlformats-officedocument.wordprocessingml.document",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:31.923Z",
      "updated_at": "2025-12-13T00:59:31.924Z"
    },
    {
      "id": null,
      "annex_number": 1,
      "document_type": null,
      "description": "AVISO DE DIFERIMIENTO DE FALLO",
      "filename": "06.00 Diferimiento de fallo N-17-2023.pdf",
      "availability": "available",
      "size_bytes": "59491",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:58.122Z",
      "updated_at": "2025-12-13T01:01:58.123Z"
    },
    {
      "id": null,
      "annex_number": 1,
      "document_type": null,
      "description": "AVISO DE DIFERIMIENTO DE FALLO",
      "filename": "07.00 Comunicado de fecha de fallo N17-2023.pdf",
      "availability": "available",
      "size_bytes": "629694",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:59.741Z",
      "updated_at": "2025-12-13T01:01:59.742Z"
    },
    {
      "id": null,
      "annex_number": 1,
      "document_type": null,
      "description": "AVISO DE DIFERIMIENTO DE FALLO",
      "filename": "08.00 Comunicado de fecha de fallo N17-2023.pdf",
      "availability": "available",
      "size_bytes": "514037",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:02:03.022Z",
      "updated_at": "2025-12-13T01:02:03.023Z"
    },
    {
      "id": null,
      "annex_number": 2,
      "document_type": null,
      "description": "ANEXO TÉCNICO",
      "filename": "01.07 ESP. TEC. CPMI KM 52+000 56+000-OK(25-mar-23)-OK.docx",
      "availability": "available",
      "size_bytes": "582590",
      "mime_type": "application/vnd.openxmlformats-officedocument.wordprocessingml.document",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:33.509Z",
      "updated_at": "2025-12-13T00:59:33.510Z"
    },
    {
      "id": null,
      "annex_number": 3,
      "document_type": null,
      "description": "MODELO DE CONTRATO",
      "filename": "01.05 Modelo del Contrato(01_PC-OP_Modalidad_Precio_Unitario_V3.2_VF).DOCX",
      "availability": "available",
      "size_bytes": "83257",
      "mime_type": "application/vnd.openxmlformats-officedocument.wordprocessingml.document",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:28.346Z",
      "updated_at": "2025-12-13T00:59:28.346Z"
    },
    {
      "id": null,
      "annex_number": 4,
      "document_type": null,
      "description": "DOC. LEGALES Y ADMON.",
      "filename": "01.02 Doc  Legales Administrativo LPN puntos y porcentajes.docx",
      "availability": "available",
      "size_bytes": "406560",
      "mime_type": "application/vnd.openxmlformats-officedocument.wordprocessingml.document",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:34.827Z",
      "updated_at": "2025-12-13T00:59:34.828Z"
    },
    {
      "id": null,
      "annex_number": 5,
      "document_type": null,
      "description": "FORMATOS TECNICOS",
      "filename": "01.03 Anexos Técnicos LPN puntos y porcentajes (002).docx",
      "availability": "available",
      "size_bytes": "515547",
      "mime_type": "application/vnd.openxmlformats-officedocument.wordprocessingml.document",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:36.275Z",
      "updated_at": "2025-12-13T00:59:36.276Z"
    },
    {
      "id": null,
      "annex_number": 6,
      "document_type": null,
      "description": "FORMATOS ECONOMICOS",
      "filename": "01.04 Anexo Economico LPN puntos y porcentajes.docx",
      "availability": "available",
      "size_bytes": "683432",
      "mime_type": "application/vnd.openxmlformats-officedocument.wordprocessingml.document",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:39.817Z",
      "updated_at": "2025-12-13T00:59:39.817Z"
    },
    {
      "id": null,
      "annex_number": 7,
      "document_type": null,
      "description": "CATALOGO DE CONCEPTOS",
      "filename": "01.06 CAT.-CPMI DEL KM 52+000 AL KM 56+000-OK.xlsx",
      "availability": "available",
      "size_bytes": "86799",
      "mime_type": "application/vnd.openxmlformats-officedocument.spreadsheetml.sheet",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:41.084Z",
      "updated_at": "2025-12-13T00:59:41.085Z"
    },
    {
      "id": null,
      "annex_number": 8,
      "document_type": null,
      "description": "FORMATO FIANZAS",
      "filename": "01.08 Modelo de fianzas.pdf",
      "availability": "available",
      "size_bytes": "294464",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:42.404Z",
      "updated_at": "2025-12-13T00:59:42.405Z"
    },
    {
      "id": null,
      "annex_number": 9,
      "document_type": null,
      "description": "LIN. SEGURIDAD SANITARIA",
      "filename": "01.09 Lineamientos_de_Seguridad_Sanitaria_F.pdf",
      "availability": "available",
      "size_bytes": "1038710",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:44.489Z",
      "updated_at": "2025-12-13T00:59:44.490Z"
    },
    {
      "id": null,
      "annex_number": 10,
      "document_type": null,
      "description": "PLANOS",
      "filename": "01.10 PL.GRAL_CP_52+000_-_56+000 (25-mar-23)-OK.dwg",
      "availability": "available",
      "size_bytes": "12583921",
      "mime_type": "application/octet-stream",
      "sha256": "8198ee28282df6ae0d26e2bcb47fee104f406681298487df719a65041a160de8",
      "uploaded_at": "2025-12-13T00:59:53.373Z",
      "updated_at": "2026-08-05T20:37:47.555Z"
    },
    {
      "id": null,
      "annex_number": 11,
      "document_type": null,
      "description": "RESUMEN CONVOCATORIA",
      "filename": "00.00 Resumen de convocatoria N16.pdf",
      "availability": "available",
      "size_bytes": "1246543",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:57.294Z",
      "updated_at": "2025-12-13T00:59:57.295Z"
    },
    {
      "id": null,
      "annex_number": 15,
      "document_type": null,
      "description": "ACTA DE VISITA AL LUGAR DE LOS TRABAJOS",
      "filename": "03.00 Acta de Visita al sitio de los trabajos -N-17-2023.pdf",
      "availability": "available",
      "size_bytes": "1249032",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T00:59:59.994Z",
      "updated_at": "2025-12-13T00:59:59.995Z"
    },
    {
      "id": null,
      "annex_number": 16,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "1.- CAT.-CPMI DEL KM 52+000 AL KM 56+000jta.xlsx",
      "availability": "available",
      "size_bytes": "88941",
      "mime_type": "application/vnd.openxmlformats-officedocument.spreadsheetml.sheet",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:01.703Z",
      "updated_at": "2025-12-13T01:00:01.705Z"
    },
    {
      "id": null,
      "annex_number": 17,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "2.- ESP. TEC. CPMI KM 52+000 56+000-OKjta.docx",
      "availability": "available",
      "size_bytes": "583011",
      "mime_type": "application/vnd.openxmlformats-officedocument.wordprocessingml.document",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:03.596Z",
      "updated_at": "2025-12-13T01:00:03.598Z"
    },
    {
      "id": null,
      "annex_number": 18,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "0-_PL.GRAL_CP_52+000_-_56+000 (25-mar-23)-OK.dwg",
      "availability": "available",
      "size_bytes": "12583921",
      "mime_type": "application/octet-stream",
      "sha256": "8198ee28282df6ae0d26e2bcb47fee104f406681298487df719a65041a160de8",
      "uploaded_at": "2025-12-13T01:00:14.448Z",
      "updated_at": "2026-08-05T20:37:47.555Z"
    },
    {
      "id": null,
      "annex_number": 19,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "PL-MPAS_BM_2.pdf",
      "availability": "available",
      "size_bytes": "49388499",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:35.240Z",
      "updated_at": "2025-12-13T01:00:35.241Z"
    },
    {
      "id": null,
      "annex_number": 20,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "Alcantarilla CP km 52+973 ZRMIRP_ ACTUALIZAC.dwg",
      "availability": "available",
      "size_bytes": "792588",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:37.691Z",
      "updated_at": "2025-12-13T01:00:37.692Z"
    },
    {
      "id": null,
      "annex_number": 21,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "Sifon CP km 52+003.30_1de3.pdf",
      "availability": "available",
      "size_bytes": "766671",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:39.181Z",
      "updated_at": "2025-12-13T01:00:39.182Z"
    },
    {
      "id": null,
      "annex_number": 22,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "Sifon CP km 52+003.30_2de3.pdf",
      "availability": "available",
      "size_bytes": "547911",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:40.867Z",
      "updated_at": "2025-12-13T01:00:40.868Z"
    },
    {
      "id": null,
      "annex_number": 23,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "Sifon CP km 52+003.30_3de3.pdf",
      "availability": "available",
      "size_bytes": "534791",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:44.977Z",
      "updated_at": "2025-12-13T01:00:44.978Z"
    },
    {
      "id": null,
      "annex_number": 24,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "Sifon CP km 52+003.30_R.02.dwg",
      "availability": "available",
      "size_bytes": "2969731",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:50.317Z",
      "updated_at": "2025-12-13T01:00:50.318Z"
    },
    {
      "id": null,
      "annex_number": 25,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-0-CHUMACERA CM-C-102.dwg",
      "availability": "available",
      "size_bytes": "854541",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:53.086Z",
      "updated_at": "2025-12-13T01:00:53.087Z"
    },
    {
      "id": null,
      "annex_number": 26,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-0-COMPUERTA RADIAL CM-C-4.dwg",
      "availability": "available",
      "size_bytes": "931451",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:00:56.581Z",
      "updated_at": "2025-12-13T01:00:56.582Z"
    },
    {
      "id": null,
      "annex_number": 27,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-0-COMPUERTA RADIAL CM-C-301.dwg",
      "availability": "available",
      "size_bytes": "984478",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:00.199Z",
      "updated_at": "2025-12-13T01:01:00.200Z"
    },
    {
      "id": null,
      "annex_number": 28,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-0-COMPUERTA RADIAL CM-C-310.dwg",
      "availability": "available",
      "size_bytes": "1787240",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:02.435Z",
      "updated_at": "2025-12-13T01:01:02.436Z"
    },
    {
      "id": null,
      "annex_number": 29,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-0-COMPUERTA RADIAL CM-C-400 H1.dwg",
      "availability": "available",
      "size_bytes": "1425669",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:04.693Z",
      "updated_at": "2025-12-13T01:01:04.694Z"
    },
    {
      "id": null,
      "annex_number": 30,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-0-COMPUERTA RADIAL CM-C-401 H2.dwg",
      "availability": "available",
      "size_bytes": "1710174",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:10.432Z",
      "updated_at": "2025-12-13T01:01:10.433Z"
    },
    {
      "id": null,
      "annex_number": 31,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-0-COMPUERTA RADIAL TM-C-452.dwg",
      "availability": "available",
      "size_bytes": "1154322",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:12.547Z",
      "updated_at": "2025-12-13T01:01:12.548Z"
    },
    {
      "id": null,
      "annex_number": 32,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-E2-1-ESTRUCTURA ALCANTARILLA PASO INFERIOR.dwg",
      "availability": "available",
      "size_bytes": "920381",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:14.482Z",
      "updated_at": "2025-12-13T01:01:14.485Z"
    },
    {
      "id": null,
      "annex_number": 33,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-E2-6-ESTRUCTURA ENTRADA DE AGUA.dwg",
      "availability": "available",
      "size_bytes": "972344",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:15.794Z",
      "updated_at": "2025-12-13T01:01:15.796Z"
    },
    {
      "id": null,
      "annex_number": 34,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-E2-7-ESTRUCTURA REPRESA COMPUERTAS RADIALES.dwg",
      "availability": "available",
      "size_bytes": "1266867",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:17.319Z",
      "updated_at": "2025-12-13T01:01:17.320Z"
    },
    {
      "id": null,
      "annex_number": 35,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-E2-8-ESTRUCTURA PUENTE VEHICULAR DE DOS CLAROS.dwg",
      "availability": "available",
      "size_bytes": "925822",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:20.470Z",
      "updated_at": "2025-12-13T01:01:20.471Z"
    },
    {
      "id": null,
      "annex_number": 36,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-E2-9-ESTRUCTURA TOMA LATERAL.dwg",
      "availability": "available",
      "size_bytes": "2499952",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:23.322Z",
      "updated_at": "2025-12-13T01:01:23.323Z"
    },
    {
      "id": null,
      "annex_number": 37,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-E3-11-ESTRUCTURA TOMA DIRECTA PARA CARCAMO DE BOMBEO.dwg",
      "availability": "available",
      "size_bytes": "1032490",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:35.284Z",
      "updated_at": "2025-12-13T01:01:35.285Z"
    },
    {
      "id": null,
      "annex_number": 38,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "Canal Principal M-Izq 52+000 - 56+000.dwg",
      "availability": "available",
      "size_bytes": "5762954",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:40.201Z",
      "updated_at": "2025-12-13T01:01:40.202Z"
    },
    {
      "id": null,
      "annex_number": 39,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "ACAD-ETAPAS CONSTRUCTIVAS.dwg",
      "availability": "available",
      "size_bytes": "1427535",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:41.958Z",
      "updated_at": "2025-12-13T01:01:41.959Z"
    },
    {
      "id": null,
      "annex_number": 40,
      "document_type": null,
      "description": "ANEXOS ACTA DE JUNTA DE ACLARACIONES",
      "filename": "SECCIONES_Canal_Principal_M-Izq 52+000 - 56+000.dwg",
      "availability": "available",
      "size_bytes": "8334437",
      "mime_type": "application/octet-stream",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:52.947Z",
      "updated_at": "2025-12-13T01:01:52.948Z"
    },
    {
      "id": null,
      "annex_number": 41,
      "document_type": null,
      "description": "ACTA JUNTA DE ACLARACIONES",
      "filename": "04.00 Acta Junta Aclaraciones  LO-16-B00-016B00002-N-17-2023.pdf",
      "availability": "available",
      "size_bytes": "1578604",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:55.212Z",
      "updated_at": "2025-12-13T01:01:55.213Z"
    },
    {
      "id": null,
      "annex_number": 42,
      "document_type": null,
      "description": "ACTA DE APERTURA DE PROPOSICIONES",
      "filename": "05.01 Acta de apertura N-17-2023_encrypted_.pdf",
      "availability": "available",
      "size_bytes": "395753",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:01:56.848Z",
      "updated_at": "2025-12-13T01:01:56.848Z"
    },
    {
      "id": null,
      "annex_number": 47,
      "document_type": null,
      "description": "ACTA DE FALLO",
      "filename": "10.00 Fallo N-17-2023.pdf",
      "availability": "available",
      "size_bytes": "26672042",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:02:26.710Z",
      "updated_at": "2025-12-13T01:02:26.711Z"
    },
    {
      "id": null,
      "annex_number": 48,
      "document_type": null,
      "description": "ANEXOS ACTA DE FALLO",
      "filename": "11.00 Comunicacion de fallo N-17-2023_encrypted_.pdf",
      "availability": "available",
      "size_bytes": "458819",
      "mime_type": "application/pdf",
      "sha256": null,
      "uploaded_at": "2025-12-13T01:02:29.438Z",
      "updated_at": "2025-12-13T01:02:29.439Z"
    }
  ],
  "alternates": [],
  "similar": [
    {
      "numero_procedimiento": "lo-16-b00-016b00002-n-16-2023",
      "nombre_procedimiento": "CONTINUACION DEL CPMI PICACHOS KM 48 AL 52, PROYECTO BALUARTE-PRESIDIO, SINALOA.",
      "dependencia": "CONAGUA",
      "siglas": "CONAGUA",
      "score": 0.008111715316772461
    },
    {
      "numero_procedimiento": "lo-16-b00-016b00002-n-25-2023",
      "nombre_procedimiento": "CONTINUACIÓN DEL CPMI DE LA PRESA PICACHOS DEL KM 56+000 AL KM 61+795, SINALOA.",
      "dependencia": "CONAGUA",
      "siglas": "CONAGUA",
      "score": 0.014271199703216553
    },
    {
      "numero_procedimiento": "lo-16-b00-016b00002-n-14-2023",
      "nombre_procedimiento": "CONSTRUCCION DEL CPMI DE LA Z.R. DE LA PRESA PICACHOS DEL KM 44 AL 48, SINALOA",
      "dependencia": "COMISION NACIONAL DEL AGUA",
      "siglas": "CONAGUA",
      "score": 0.03500938415527344
    },
    {
      "numero_procedimiento": "lo-16-b00-016b00002-n-13-2023",
      "nombre_procedimiento": "CONSTRUCCION DEL CPMI DE LA Z.R. DE LA PRESA PICACHOS DEL KM 39 AL 44, SINALOA",
      "dependencia": "CONAGUA",
      "siglas": "CONAGUA",
      "score": 0.04369884729385376
    },
    {
      "numero_procedimiento": "lo-16-b00-016b00002-n-44-2023",
      "nombre_procedimiento": "CONSTRUCCION CPMI KM 27+652.52 AL 32+340, PROYECTO BALUARTE-PRESIDIO, SINALOA",
      "dependencia": "CONAGUA",
      "siglas": "CONAGUA",
      "score": 0.06142646074295044
    },
    {
      "numero_procedimiento": "lo-16-b00-016b00002-n-45-2023",
      "nombre_procedimiento": "CONSTRUCCION CPMI KM 32+340 AL KM 37+340, MPIO ROSARIO, SINALOA",
      "dependencia": "CONAGUA",
      "siglas": "CONAGUA",
      "score": 0.06543457508087158
    }
  ]
}